Client Brief
We were approached by an independent school to assist with extra modular classroom facilities, including a science lab and also a reception office. The school required us to take on the whole project from groundworksto final building control sign-off.
- CLIENT:
Greenroom School - LOCATION:
Kingsley, Hampshire - SIZE:
15m x 10m - SECTOR:
Education - TYPE:
5 Bay single storey single storey modular - COMPLETION WITHIN:
14 weeks - TIME ON SITE:
10 weeks
Key Facts
The Results
Due to the school’s slight delay in receiving planning permission, we didn’t have much time to mobilise and put together the pre-owned steel frames. Once we selected the steel module frames, we very quickly stripped and started construction of the refurbished classroom facility. We delivered the building immediately after construction. The client was delighted with the finished building; it looked very modern and sharp.
Challenges We Faced
The client wanted to install a concertina partition wall, which happened to be quite heavy. So we had to instruct a structural engineer to create a steel structural design. We then instructed a steel fabrication company to supply and fit the steelworksto the module frame. The client successfully fitted their concertina wall with no issues.